Spherical Angle Home   FAQs   |  Support   |  Downloads   
 
Critical Chain Software for Microsoft® Project
   Home   |    Contact Us   |    Tell a Friend   |    Newsletter   |    Privacy Policy
 Search for
  
Products
    cc-PulseTM
        Overview
        Reports
        The Looking GlassTM
        FREE Download of cc-Pulse
    cc-MPulseTM
    The Looking GlassTM
    Pricing & Maintenance
Software Training
    Overview
    Jump Start
    Intro to MS Project
    cc-Pulse - Single Project Scheduling
Academic Program
    Program Details
Resellers
    Application
About Us
    Mission Statement
    Company Information
    Biographies
Frequently Asked Questions: Limitations

Is cc-Pulse limited to scheduling 1,000 tasks?

No, cc-Pulse is not limited to scheduling 1,000 tasks. You are limited by the amount of memory available to Microsoft Project.

See also:
Differences in Feature Capacities for Microsoft Project 1.x - 2000


Why is linking summary tasks to other tasks not allowed?


The problem with linking summary tasks to anything is that the summary tasks are not a valid model of the sub tasks underneath.

The summary bar represents the span from the scheduled start of the first child, to the scheduled finish of the latest child.

This is a deterministic model, and does not represent the expected span of the sub tasks, nor does it have any way to represent the safe span of the sub tasks.

Summary tasks are useful for organizing the tasks, but must not be used to affect the position of the sub tasks.